AA Design + Make Masters study at the Architectural Association Hooke Park

South Lodge

The South Lodge consists of two bedrooms and a shared kitchen-dining-living space. This student designed-and-built timber-framed building uses recycled local materials, salvaged, and up-cycled objects. It has been developed through a series of full-scale prototype mock-ups to tailor the design to the site and anticipated occupation. Constructed started in 2013 and the project was completed in 2014.

Student design-make team: Carlos Chen, Stephanie Cramer, Sarina da Costa Gomez, Joseph Dacoronias-Marina, Elizabeth Lawrence.

The project received an Honorable Mention at the International Architecture Awards 2015.

 

  • The finished building September 28, 2014

    The completed building is now connected to the woodchip-fueled district heating system.

  • Lodge inhabited! August 28, 2014

    Design & Make students Satta and Yingzi are testing out the lodge – and the furniture designed and made by graduates of the Lyme Regis Boat Building Academy in a visiting workshop at Hooke Park in June.

  • Cladding completed March 28, 2014

    The cladding consists of western red cedar from Hooke Park that has been sawn through-and-through and then cut into planks. The offset waney-edges are placed between the planks at 90 degrees to expose the original tree section profile – which is seen most dramatically near sunset when long shadows are cast across the walls.

  • Bedroom wing completed January 20, 2014

    The bedrooms and bathroom are finished; the reclaimed glazing for the social space is being installed.

  • Nearly there… November 24, 2013

    A few dusk and interior shots. The timber cladding is complete, windows are in and the interior is in the final stages.

  • SummerBuild 2013 – Phase 2 October 4, 2013


    SummerBuild Phase 2

  • SummerBuild Phase 2 September 5, 2013

    The second group of volunteers are at Hooke Park helping in the waterproofing, insulation, services and timber framing of Student Lodge 3.

  • SummerBuild 2013 – Phase 1 August 10, 2013

    Volunteer students on the ‘SummerBuild’ programme have been assisting the D&M team with completing the erection of the timber frame.

  • Window making July 26, 2013

    Window making.

  • Bedroom wall and roof assembly July 25, 2013

    Bedroom wall and roof assembly.

  • First wall installation July 23, 2013

    Wall #1 being installed over the deck after its prefabrication stage was completed in the Big Shed.

  • Deck beam assembly July 5, 2013

    Design & Make students coordinating the transport and assembly of the main deck beams over the foundation piles.

     

     

  • Project background July 4, 2013

    Ph1_4 Ph1_5 Ph1_6